Modernizing power monitoring for South Carolina's busiest airport for real-time anomaly response
- switchgears
- 2
- power meters
- 200+
- power circuits
- 500+
Challenges
The client needed real-time visibility of critical power systems to support reliable airport operations.
Legacy serial-connected devices prevented centralized monitoring and timely identification of power anomalies across airport facilities.
The engagement required integration of two switchgear lineups, 200 power meters, and more than 500 monitored circuits.
Technologies
- EMCS
- Moxa gateways
- switchgear
- power meters
- serial-to-Internet Protocol connectivity
Solution
Implemented an EMCS system for airport-wide monitoring of critical power systems.
Performed an as-built assessment and integrated legacy serial devices through Moxa gateway hardware for centralized monitoring.
Configured real-time data, alarms, and remote access to help facilities teams investigate power anomalies before operations were affected.
Verified connectivity and data transmission across switchgear, power meters, and monitored circuits before operational handover.
Outcomes delivered
Enabled real-time alerts for critical airport power anomalies.
Expanded visibility across 200 meters and 500+ circuits.
Provided remote monitoring access for facilities response teams.
Supported reliable operations at South Carolina’s busiest airport.