Challenges
The client needed stable and precise environmental control for 300+ control panels across 20+ data centers.
HVAC equipment required integration into centralized BAS platforms to optimize performance and reliability.
The work required design, engineering, programming, point-to-point testing, cutover, commissioning, and documented closeout within high-availability precision environmental-control environments.
Technologies
- BMS platforms
- HVAC equipment
- PLC systems
- Distech Controllers
- Niagara Framework
- point-to-point testing
- Procore
Solution
Delivered full-lifecycle BAS spanning design, engineering, point-to-point testing, cutover, commissioning, and closeout across 20 data centers.
Integrated HVAC equipment into centralized BMS platforms to coordinate control across approximately 1GW+ capacity.
Upgraded PLC systems to improve control accuracy, reliability, and maintainability within precision environmental-control environments supporting more than 2,500 equipment racks.
Completed commissioning and documented closeout to validate the planned BAS scope and support operational transition.
Outcomes delivered
Integrated control across 20 critical data centers totaling over 1GW capacity in retrofit environment.
High-precision environmental control for 2,500+ racks.
Coordinated BAS and PLC operations.