Case study

Decommissioning 51 legacy USAF telecom cabinets to prepare core facilities for mission upgrades

TelecomBusiness Solutions
largest DoD test complex
2nd
personnel
19,000+
cabinets across buildings
51

Challenges

  • Eglin Air Force Base needed to retire 51 obsolete telecom cabinets while protecting active equipment, power systems, and distribution infrastructure.

  • Equipment across three buildings required a controlled site-by-site plan for cabinets, battery plant cables, and line cabling.

  • The removal scope had to avoid damage to live network equipment, power systems, and active distribution frame boundaries.

Technologies

  • Main distribution frame (MDF)
  • -48 volt direct-current battery cabling
  • telecommunications cabinets
  • line cabling
  • floor anchors
  • site-by-site removal sequencing

Solution

  • Removed specified cabinets and in-scope power and line cabling through a controlled sequence coordinated with the technical point of contact.

  • Collected spare cards and scrap material, cleared floor anchors, and completed room cleaning to return spaces to usable condition.

  • Protected active Main Distribution Frame (MDF), power, and network boundaries while coordinating access, escorts, and telecommunications practices.

Outcomes delivered

  • Decommissioned 51 legacy telecommunications cabinets across three buildings.

  • Cleared obsolete cabling, anchors, and hardware from usable spaces.

  • Protected active network, power, and distribution-frame boundaries during removal sequences.

  • Prepared facilities for future mission-system upgrade installation work.

Next success story

Decommissioning legacy data center equipment for an Air Force Reserve facility transition

Read next
GET IN TOUCH

Take The First Step Towards Reliable Controls Integration.

Tell us about your project, your challenges, and what success looks like. We’ll follow up with a tailored approach.

Opens your email app with your message ready to send. Privacy Policy